Cheat Sheet — Part 1: Pre-Sales, Estimation & Consulting

581 words · about 3 min

Key Terms

Term In one line
RFI Request for Information — prove capability, no pricing yet
RFP Request for Proposal — full solution and price
RFQ Request for Quotation — price only; solution already chosen
SOW Statement of Work — the contractual deliverables, timeline, cost
Orals The live bid presentation and Q&A; often where the deal is actually won
PoC Proof of Concept — validates that it can work technically
PoV Point of Value — validates that it’s worth doing, in business numbers
MoSCoW Must / Should / Could / Won’t — scope prioritization under a fixed budget
WBS Work Breakdown Structure — decompose to tasks, estimate bottom-up
FPA Function Point Analysis — size by functionality (EI/EO/EQ/ILF/EIF), not by lines of code

Numbers That Matter

Figure Value Where it bites
Solution workshop 1–2 days on site Too short and you’re guessing; too long and you’ve burned pre-sales budget
Contingency +20–30% For unknown complexity — state it openly rather than burying it
FPA conversion ~8 hrs per function point 199 FP × 8 = 1,592 hours; the ratio is what interviewers probe
Dialogue in orals ~30% of the slot Monologue presentations lose to conversations
T-shirt sizing XS <100 · S 100–300 · M 300–800 · L 800–2,000 · XL >2,000 person-days The agile pre-sales shorthand
Three-point estimate (O + 4M + P) / 6 PERT weighting — quote a range, never a point

Decision Rules

  • Use WBS when requirements are known and decomposable — it gives defensible bottom-up numbers. Use FPA when the program is large and multi-year and WBS would be absurdly granular, or you’re benchmarking productivity across projects. Use analogous/parametric when you have a comparable past project and little time.
  • Use T-shirt sizing when you’re still in the qualification stage and precision would be false confidence.
  • Budget 40% below your estimate? Don’t discount the rate — cut scope with MoSCoW, propose a phased delivery, and keep the day rate intact. Discounting signals your first number was padded.
  • PoC vs PoV: if the client doubts feasibility, run a PoC. If they doubt value, a PoC won’t move them — run a PoV with a measured business metric.
  • State assumptions explicitly rather than hedging: “I’m assuming 99.9% availability. Is that correct?” An unstated assumption becomes a change request later.
  • Structure every capability pitch as a pyramid: business problem first, architectural thinking second, technical depth third — and stop at the level your audience is at.

Say This Out Loud

“I start with a discovery call to understand the pain point, and I actively resist jumping to a solution — I use 5-Whys thinking to get below the symptom to the root cause. Only then do I shape an architecture, because the architecture that wins is the one that visibly maps to their problem, not the one with the most boxes.”

“I never quote a single number. I quote a range with the assumptions attached, and I name the contingency out loud — usually 20 to 30 percent for unknown complexity. If a client pushes back on the range, that’s a scope conversation, not a pricing conversation, and I’ll take them through MoSCoW to find what actually has to ship in phase one.”

“On scope creep: acknowledge, assess impact, present trade-offs, get a decision. Every new request is welcome — it just has to come with an explicit answer to what moves out, or what the change costs. The formal change-request process isn’t bureaucracy, it’s what keeps the relationship honest.”