Key Terms
| Term | In one line |
|---|---|
| RFI | Request for Information — prove capability, no pricing yet |
| RFP | Request for Proposal — full solution and price |
| RFQ | Request for Quotation — price only; solution already chosen |
| SOW | Statement of Work — the contractual deliverables, timeline, cost |
| Orals | The live bid presentation and Q&A; often where the deal is actually won |
| PoC | Proof of Concept — validates that it can work technically |
| PoV | Point of Value — validates that it’s worth doing, in business numbers |
| MoSCoW | Must / Should / Could / Won’t — scope prioritization under a fixed budget |
| WBS | Work Breakdown Structure — decompose to tasks, estimate bottom-up |
| FPA | Function Point Analysis — size by functionality (EI/EO/EQ/ILF/EIF), not by lines of code |
Numbers That Matter
| Figure | Value | Where it bites |
|---|---|---|
| Solution workshop | 1–2 days on site | Too short and you’re guessing; too long and you’ve burned pre-sales budget |
| Contingency | +20–30% | For unknown complexity — state it openly rather than burying it |
| FPA conversion | ~8 hrs per function point | 199 FP × 8 = 1,592 hours; the ratio is what interviewers probe |
| Dialogue in orals | ~30% of the slot | Monologue presentations lose to conversations |
| T-shirt sizing | XS <100 · S 100–300 · M 300–800 · L 800–2,000 · XL >2,000 person-days | The agile pre-sales shorthand |
| Three-point estimate | (O + 4M + P) / 6 | PERT weighting — quote a range, never a point |
Decision Rules
- Use WBS when requirements are known and decomposable — it gives defensible bottom-up numbers. Use FPA when the program is large and multi-year and WBS would be absurdly granular, or you’re benchmarking productivity across projects. Use analogous/parametric when you have a comparable past project and little time.
- Use T-shirt sizing when you’re still in the qualification stage and precision would be false confidence.
- Budget 40% below your estimate? Don’t discount the rate — cut scope with MoSCoW, propose a phased delivery, and keep the day rate intact. Discounting signals your first number was padded.
- PoC vs PoV: if the client doubts feasibility, run a PoC. If they doubt value, a PoC won’t move them — run a PoV with a measured business metric.
- State assumptions explicitly rather than hedging: “I’m assuming 99.9% availability. Is that correct?” An unstated assumption becomes a change request later.
- Structure every capability pitch as a pyramid: business problem first, architectural thinking second, technical depth third — and stop at the level your audience is at.
Say This Out Loud
“I start with a discovery call to understand the pain point, and I actively resist jumping to a solution — I use 5-Whys thinking to get below the symptom to the root cause. Only then do I shape an architecture, because the architecture that wins is the one that visibly maps to their problem, not the one with the most boxes.”
“I never quote a single number. I quote a range with the assumptions attached, and I name the contingency out loud — usually 20 to 30 percent for unknown complexity. If a client pushes back on the range, that’s a scope conversation, not a pricing conversation, and I’ll take them through MoSCoW to find what actually has to ship in phase one.”
“On scope creep: acknowledge, assess impact, present trade-offs, get a decision. Every new request is welcome — it just has to come with an explicit answer to what moves out, or what the change costs. The formal change-request process isn’t bureaucracy, it’s what keeps the relationship honest.”