2.1 WBS (Work Breakdown Structure)
A hierarchical decomposition of all project work into estimable components.
Project: E-Commerce Platform Modernization
├── 1. Discovery & Architecture
│ ├── 1.1 Current State Assessment (40h)
│ ├── 1.2 Architecture Design (80h)
│ └── 1.3 PoC Development (120h)
├── 2. Core Platform Development
│ ├── 2.1 User Service (200h)
│ ├── 2.2 Product Service (160h)
│ ├── 2.3 Order Service (240h)
│ └── 2.4 Payment Service (180h)
├── 3. Infrastructure & DevOps
│ ├── 3.1 Cloud Infrastructure Setup (80h)
│ ├── 3.2 CI/CD Pipeline (60h)
│ └── 3.3 Monitoring & Observability (40h)
├── 4. Testing
│ ├── 4.1 Unit & Integration Testing (20% of dev)
│ ├── 4.2 Performance Testing (80h)
│ └── 4.3 Security Testing (40h)
└── 5. Deployment & Hypercare
├── 5.1 UAT Support (60h)
└── 5.2 Go-Live & Stabilization (80h)
WBS best practices:
- Decompose 3–4 levels deep for accuracy
- Every leaf node should be independently estimable
- Add 20–30% contingency for unknown complexity
- Include non-development tasks: architecture, DevOps, PM, QA, documentation
2.2 Function Point Analysis (FPA)
Measures functionality delivered from the user’s perspective, independent of technology.
The 5 function types:
| Type | Description | Weights (Simple/Avg/Complex) |
|---|---|---|
| EI (External Input) | Data entering the system | 3 / 4 / 6 |
| EO (External Output) | Data leaving the system | 4 / 5 / 7 |
| EQ (External Query) | Read-only retrieval | 3 / 4 / 6 |
| ILF (Internal Logical File) | Data maintained by the system | 7 / 10 / 15 |
| EIF (External Interface File) | External data referenced | 5 / 7 / 10 |
FPA calculation:
Raw FP = Σ (Count × Weight for each function type)
VAF (Value Adjustment Factor) = 0.65 + (0.01 × Σ of 14 General System Characteristics)
Adjusted FP = Raw FP × VAF
Effort = Adjusted FP × Productivity Rate (e.g., 8 hours/FP for Java microservices)
Example calculation:
- 10 EI (avg=4) = 40, 8 EO (avg=5) = 40, 12 EQ (avg=4) = 48, 5 ILF (avg=10) = 50, 3 EIF (avg=7) = 21
- Raw FP = 40+40+48+50+21 = 199
- Assume GSC total = 35 → VAF = 0.65 + 0.35 = 1.00
- Adjusted FP = 199
- Effort at 8 hrs/FP = 1,592 hours
When to use FPA: requirements are functional/user-facing; large multi-year programs where WBS would be too granular; benchmarking productivity across projects.
2.3 Analogous / Parametric Estimation
Use past similar projects as anchors:
"Our last microservices migration of similar complexity took 18 months and
2,000 person-days. This project is ~20% more complex due to legacy
integrations. Estimate: 2,400 person-days + 15% risk buffer = 2,760 person-days."
2.4 T-Shirt Sizing (Agile pre-sales)
| Size | Effort | Duration |
|---|---|---|
| XS | < 100 person-days | 1–2 months |
| S | 100–300 person-days | 2–4 months |
| M | 300–800 person-days | 4–8 months |
| L | 800–2,000 person-days | 8–18 months |
| XL | > 2,000 person-days | > 18 months |
2.5 Three-Point Estimation
Estimate = (Optimistic + 4×Most_Likely + Pessimistic) / 6
Used to account for uncertainty when historical data is thin.