Section 2

Estimation Techniques

478 words · about 2 min

2.1 WBS (Work Breakdown Structure)

A hierarchical decomposition of all project work into estimable components.

Project: E-Commerce Platform Modernization
├── 1. Discovery & Architecture
│   ├── 1.1 Current State Assessment (40h)
│   ├── 1.2 Architecture Design (80h)
│   └── 1.3 PoC Development (120h)
├── 2. Core Platform Development
│   ├── 2.1 User Service (200h)
│   ├── 2.2 Product Service (160h)
│   ├── 2.3 Order Service (240h)
│   └── 2.4 Payment Service (180h)
├── 3. Infrastructure & DevOps
│   ├── 3.1 Cloud Infrastructure Setup (80h)
│   ├── 3.2 CI/CD Pipeline (60h)
│   └── 3.3 Monitoring & Observability (40h)
├── 4. Testing
│   ├── 4.1 Unit & Integration Testing (20% of dev)
│   ├── 4.2 Performance Testing (80h)
│   └── 4.3 Security Testing (40h)
└── 5. Deployment & Hypercare
    ├── 5.1 UAT Support (60h)
    └── 5.2 Go-Live & Stabilization (80h)

WBS best practices:

  • Decompose 3–4 levels deep for accuracy
  • Every leaf node should be independently estimable
  • Add 20–30% contingency for unknown complexity
  • Include non-development tasks: architecture, DevOps, PM, QA, documentation

2.2 Function Point Analysis (FPA)

Measures functionality delivered from the user’s perspective, independent of technology.

The 5 function types:

Type Description Weights (Simple/Avg/Complex)
EI (External Input) Data entering the system 3 / 4 / 6
EO (External Output) Data leaving the system 4 / 5 / 7
EQ (External Query) Read-only retrieval 3 / 4 / 6
ILF (Internal Logical File) Data maintained by the system 7 / 10 / 15
EIF (External Interface File) External data referenced 5 / 7 / 10

FPA calculation:

Raw FP = Σ (Count × Weight for each function type)
VAF (Value Adjustment Factor) = 0.65 + (0.01 × Σ of 14 General System Characteristics)
Adjusted FP = Raw FP × VAF
Effort = Adjusted FP × Productivity Rate (e.g., 8 hours/FP for Java microservices)

Example calculation:

  • 10 EI (avg=4) = 40, 8 EO (avg=5) = 40, 12 EQ (avg=4) = 48, 5 ILF (avg=10) = 50, 3 EIF (avg=7) = 21
  • Raw FP = 40+40+48+50+21 = 199
  • Assume GSC total = 35 → VAF = 0.65 + 0.35 = 1.00
  • Adjusted FP = 199
  • Effort at 8 hrs/FP = 1,592 hours

When to use FPA: requirements are functional/user-facing; large multi-year programs where WBS would be too granular; benchmarking productivity across projects.

2.3 Analogous / Parametric Estimation

Use past similar projects as anchors:

"Our last microservices migration of similar complexity took 18 months and
2,000 person-days. This project is ~20% more complex due to legacy
integrations. Estimate: 2,400 person-days + 15% risk buffer = 2,760 person-days."

2.4 T-Shirt Sizing (Agile pre-sales)

Size Effort Duration
XS < 100 person-days 1–2 months
S 100–300 person-days 2–4 months
M 300–800 person-days 4–8 months
L 800–2,000 person-days 8–18 months
XL > 2,000 person-days > 18 months

2.5 Three-Point Estimation

Estimate = (Optimistic + 4×Most_Likely + Pessimistic) / 6

Used to account for uncertainty when historical data is thin.